DUBOIS – Three Construction Projects for DuBois School are on schedule for completion.
Currently crews are working on the High School Walkway and are in the preliminary construction phases, as the contractors begin grading some areas and reviewing construction areas. This project is expected to be completed in July this year.
The resurfacing of the High School track has already started with crews having already removed the rubber track surface. Contractors are now beginning to evaluate what portions need to be milled before making a stable pavement to reseal. This is expected to be completed by the end of August.
The reconstruction of Mansell Stadium is well underway with most deconstruction completed. Crews are now waiting for equipment to arrive and a plan to install boilers. This project is slated to end on September 17th.